Temporary railway line in Vught makes way for the future
Building a temporary railway line may sound straightforward, but in Vught the bar was set high. For the Vught Verdiept project, the existing railway line had to be relocated to create space for the construction of a tunnel and a sunken railway alignment. A temporary bypass was therefore built that will need to operate reliably for five years. During this extensive project, which included a sixteen-day track possession, this technical puzzle was put together. Our role? Delivering all the materials needed to make this construction possible, just in time.
Materials that made the project possible
To realise this bypass within the required timeframe, materials were needed that could be used immediately and met ProRail’s strict technical requirements. All products were delivered to the track just in time.
The kilometres of rails used for this project were coated by us in advance. Thanks to the head coating, applied on our own coating line at the same time as the rubber coating on the sides, the rails were optimally prepared for later embedding at level crossings. The quality of this coating is more consistent than when it is applied on site, where drying times and weather conditions have a greater impact. This saves considerable time on site and means the rails are ready for immediate installation.
We also supplied ballast, both by road and by rail wagon. Insulated rail joints, ETM materials such as rail coils and cable lugs, guide rail crossings, buffer stops and relays were also part of this extensive project delivery.
The relays play a crucial role in the temporary installation and require specific expertise and availability. Thanks to our many years of experience in relay management, we were able to respond effectively to these requirements within the project schedule.
Timing is everything
The track possession required tight project coordination and a logistics process that had to be right down to the smallest detail. By carefully planning material flows, responding quickly and clearly coordinating technical decisions, all components arrived at the right place at exactly the right time. This created stability and predictability during a period in which the schedule allowed little room for deviation. Organising and streamlining this process played an important role in ensuring the work progressed smoothly.
A temporary bypass with a long-term role
Although the bypass is temporary, it will be used intensively for five years. This requires reliable materials and partners who understand what is needed to keep a project of this scale running without delays. With our products and expertise, we were able to make a valuable contribution.